Unloading Upon Arrival

The transport vehicles have a length of up to 18 m with headroom not to exceed 4 m. The construct team must ensure that the crane has unimpeded access to the site, taking into account possible street obstructions, overhead wires, the sharpness of bends, parked vehicles and clear view during placement.

When the panels arrive at the site, they will be vertically lifted directly from the transport and moved into position sequentially. The contractor will have an electronic reader and sequential plan to monitor the removal of panels and to ensure the proper sequence of construct as determined by the blueprints.

Spreader bars must be used in conjunction with the crane lift system to guarantee an angle of 90 degrees. The construction team must ensure that the panel element is always level, using cables if necessary.

Next: Placement, Fastening & Clamping

At Vidabode Group, we seek to be a world class company, but we also seek to better the world. Our goal is to put babies and families into safe and affordable homes.  Read more.

Vidabode sales agencies working with prospective licensees to develop manufacturing and distribution opportunities within specific geographical regions. Read more.

We need better building materials because of natural disasters, political strife, changing demographics, urbanization, and a need for green technologies.  Read more.